Mechanical/Electrical/Safety
•Emergency Power Cut-Off
•Compressed Air Dryer
•Backup Compressor
•Two 240-Ton Chillers
•Dehumidifier (Depot Level Maintenance)
•0.5 and 5 micron Continuous Trended Particle Counters
•High-Pressure GN2 System
•Continuously Monitored Hydrocarbon Sensors
•Continuously Monitored Hypergolic Sensors
•Weather Station
•30-Ton Tower Crane and Readout
•30-Ton & 75-Ton Crane Laser Pointers
•Coffer Door (Door between Highbay and Upper Tower) made to roll back on rails
•Upper Tower Main Doors changed from guillotine to swinging
•N2O4 and N2H4 Scrubber Pads
•ESD Floors (Highbay, Cells, Airlock)
•Remote DDC Monitoring (continuously upgraded)
•275 KVA UPS
•Enlarged Break Room
Communications
•Range digital transport from OC-3 to OC-12
•Range Video from Analog to Digital
•New Timing and Video Systems
•New Channel Banks
•New Range WDM Fiber Transport
•Expanded PBX
•Expanded Internet Connectivity
•T1 Capability to Range Expanded to 28 redundant
•DS-3 Capability to Range Expanded to 3 Redundant
•New Telemux-100 Telemetry Interface 0-30 Mbs